We use cookies to improve your online experience. By continuing browsing this website, we assume you agree our use of cookies.

Solar DC String Box YBS-2/2 Cuts PV Commissioning Time by 35%

Views : 48
Update time : 2026-08-11 13:01:23

What kind of customer adopted the YBS-2/2?

A mid-sized solar EPC contractor based in southern Spain took on a 12 MWp ground-mounted PV project in 2024. The company handles the full delivery chain, from engineering to grid connection, and operates across three provinces. Its in-house installation crews had grown over two years, but the engineering team remained small. For this project, the client specified a DC system with 32 strings per combiner cabinet and a 1500 V DC bus. The contractor needed a solar DC string box that could be deployed, reduced wiring mistakes, and met the latest European installation standards.

What problems did the old string-box approach create?

Before switching to the SOLAR DC STRING BOX YBS-2/2, the contractor used generic DC junction boxes assembled on site. Each box required separate procurement of terminal blocks, fuse holders, and surge arresters. Electricians then had to cut cables to length, crimp lugs, and wire each string individually. That approach created three recurring problems:

  • Polarity inversion errors appeared in roughly 4% of the strings, discovered only during insulation testing.
  • Loose terminal connections provoked hot spots and intermittent ground-fault alarms, forcing rework after commissioning.
  • Commissioning of each 3 MW block took up to 14 days because every termination had to be physically checked.

These failures extended the project calendar and increased labor costs. The contractor estimated that rework and delayed grid-connection penalties consumed up to 9% of the total installation budget.

Why did the customer choose the SOLAR DC STRING BOX YBS-2/2?

The engineering team assessed three alternatives: a conventional field-assembled box, a custom-built cabinet from a local panel shop, and the SOLAR DC STRING BOX YBS-2/2 from singielectric. The first option repeated the same quality control problems. The second offered flexibility but required a long lead time and still needed on-site wiring. The YBS-2/2 stood out because it arrives as a fully wired, pre-tested unit. Its compact design integrates string fuse disconnectors, surge protection devices, and a DC isolating switch inside an IP65 enclosure. The input terminals accept up to 4 mm² cable, which matches the contractor's standard PV1-F wiring specification.

The decision was also driven by compliance. The unit is designed to support safe isolation and overamperage protection in line with IEC 60364-7-712 requirements for PV supply systems. That gave the EPC company confidence it would pass the inspector's review without custom engineering work.

How was the YBS-2/2 deployed on site?

The deployment took place over a six-week period across three substations. The methodology was straightforward:

  1. The engineering team defined string groupings and chosen 20 units of the YBS-2/2, each handling two inputs per string.
  2. Each box was mounted on the pre-installed steel structure using the factory-fitted mounting brackets. No additional enclosure fabrication was needed.
  3. PV string cables were connected to the labeled terminals. The integrated fuse holders eliminated separate fuse wiring.
  4. DC output cables were routed to the inverter through the factory-sealed cable glands.
  5. Commissioning engineers performed insulation resistance checks and polarity verification. Because the internal wiring was factory-tested, they only validated the external connections.

A typical challenge appeared during the second substation: two strings produced unexpectedly low volt-level. The fault was traced to a damaged PV connector, not the string box. The YBS-2/2's clear labeling and segregated terminal layout let technicians isolate the problem in under 30 minutes, instead of tracing wiring across a full cabinet.

What measurable improvements did the YBS-2/2 deliver?

Over the complete 12 MWp project, the results were recorded against the previous installation method:

  • Commissioning time per 3 MW block dropped from 14 days to 9 days, a 36% reduction.
  • String polarity errors fell to zero, compared with the previous 4% error rate.
  • Rework hours caused by DC-side terminations decreased by 80%.
  • Total installation cost for the DC collection system was reduced by roughly 18%, from lower labor and rework expenses.
  • Grid connection was achieved 11 days earlier than the contractual deadline, avoiding penalty charges estimated at $9,000 per day.

Beyond the numbers, the project team gained a cleaner handover process. The as-built documentation was simpler because the YBS-2/2's internal schematics already matched the physical layout, leaving less room for interpretation.

What did the customer say the project?

The EPC company's electrical site manager commented: "The YBS-2/2 took the most error-prone part of DC installation and turned it into a plug-and-play step. We finished commissioning ahead of schedule, and the inspectors found no issues with the string boxes."

What can other PV developers learn from this case?

Three lessons from this project apply to any large-scale PV installer:

  1. Pre-wired solutions reduce site risk. The YBS-2/2's factory wiring removes a large share of human errors that are difficult to detect without intensive testing.
  2. Compliance-based choice pays off. Choosing a string box that aligns with IEC 60364-7-712 and IEC 60947-1 simplifies the approval process and avoids last-minute redesigns.
  3. Measure the cost of rework, not unit price. A slightly higher component cost is offset by lower labor, fewer test failures, and earlier grid connection.

If the project were repeated, the engineering team says it would order the YBS-2/2 earlier in the design phase to standardize the cable schedule from day one. That small change could compress the engineering lead time by another week.

Standards and references

This case study references the following industry standards:

SOLAR DC STRING BOX YBS-2/2